A delay of two years and an additional cost of DKK 685 million.
The Italian contractor on the Storstrøm Bridge, SBJV, believes that the consequences of what they perceive as changed requirements for the bridge design, related to the risk of collisions or ship impacts, are a two-year delay and an additional cost of DKK 685 million. This information is stated in a complaint submitted to the Arbitration Institute which FemernNews has gained access to.