Heavy-duty floating dock in action

The floating gate, which is meant to close and seal the deep basins outside the tunnel factory, has been tested for the first time

Another milestone.

SIGN UP FOR THE NEWSLETTER

That's how Femern A/S describes the recent achievement: just before the weekend storm, they moved the 21-meter-high floating gate for the first time. The gate seals the deep basins before the tunnel elements can be towed out.

- We can now check off another milestone from our checklist - we have moved our floating gate for the first time which until now has been located in the middle of basin B where it was cast, Femern posted on Facebook about the test.