The excavation of the tunnel trench is 95 percent complete in terms of volume. However, it will take 6-12 months before the entire seabed stretch is ready to receive the first tunnel elements.
Femern A/S expects to be completely finished with this part of the mega-project by the end of 2024. There is a good reason why the last part of the work takes time, as explained by Jens Ole Kaslund, Technical Director at Femern A/S.