The excavation of the tunnel trench is 95 percent complete in terms of volume. However, it will take 6-12 months before the entire seabed stretch is ready to receive the first tunnel elements.
SIGN UP FOR THE NEWSLETTER
Femern A/S expects to be completely finished with this part of the mega-project by the end of 2024. There is a good reason why...
Tunnel trench taking shape: Sandpaper replaces the planer
The excavation of the tunnel trench is 95 percent complete. We're putting away the planer and getting out the sandpaper, says the Technical Director of Femern A/S
Vessels like Vox Amalia, working on the Femern Link project, are dredging the seabed for approximately 13 million cubic meters of material. Van Oord