"We need 80% more reinforcement than what was tendered"

The contractor for the Storstrøm Bridge, SBJV, is complaining about significant increases in material consumption and raw material prices on the delayed bridge project. This is happening in an internal letter to the Danish Road Directorate (Vejdirektoratet)

The upcoming arbitration case between the contractor for the Storstrøm Bridge, SBJV and the Danish Road Directorate (Vejdirektoratet) as the client, revolves, among other things, around rising prices and access to raw materials.

SIGN UP FOR THE NEWSLETTER

This is evident from a letter from the then project director, Aldo Catteneo, to the Danish Road Directorate (Vejdirektoratet) which FemernNews has gained access to through a freedom of information request.

BREAKING
{{ article.headline }}